Parnell & Associate’s will be conducting street paving and repair next week. The Village is also jointly working with Union Township on various road repairs. All work is weather dependent and “No Parking” signs will be posted as necessary. Please contact Village Hall with any questions or concerns at (740) 826-7671.
Work will occur on Monday afternoon, 8/17, or Tuesday morning, 8/18
• Reservoir Rd – short section from Maple lane headed north approx. 1,000’
• Shadyside Drive – Main Street headed north approx. 500’
Work will occur most of the day(s) on Tuesday, 8/25, or Wednesday, 8/26
• High Street (between Stormont St and College Drive)
• South Liberty Rd (55’ overlay on concrete bridge)
• Garfield Avenue (Main Street to crest of hill heading northbound)
• Hawthorn Drive – asphalt curb to divert stormwater
• Chestnut Alley – asphalt curb to divert stormwater